Latrobe Magnesium starts furnace heating as first metal target approaches
Latrobe Magnesium’s Phase 1B demonstration project is now fully installed and 78% commissioned, with furnace heating under way ahead of targeted first magnesium metal by the end of 2026. The company says the project remains within its original A$6.1 million budget.
- Phase 1B installation reaches 100% completion
- Commissioning advances to 78% from 50%
- Furnace heating begins ahead of ore commissioning
- First magnesium crowns above 98% Mg targeted by year-end
- Project forecast remains within A$6.1 million budget
Add us as a preferred source on Google
Furnace heating begins ahead of first metal
Latrobe Magnesium Limited (ASX:LMG) has reached the most advanced stage yet at its Victorian demonstration plant, with the Phase 1B project fully installed and its furnace now undergoing staged heating. Commissioning has reached 78%, up from 50% at 31 October, leaving the company targeting its first magnesium metal crowns with purity above 98% by the end of 2026.

The progress marks a further step beyond the 50% commissioning milestone, when installation stood at 98% and the same year-end first-metal target remained in place. Latrobe says the final furnace seal was installed after ignition testing, while loading systems testing continues alongside heat-up.
Briquettes ready for retort feed

The briquetting plant has completed ore commissioning, including reagent milling and briquetting, and has produced its first batch of magnesium oxide feed briquettes. Those briquettes are awaiting feed to the retort, where the next commissioning phase will depend on completion of furnace heating.
Latrobe’s stated sequence is now clear but not yet complete: furnace heat-up must be followed by final ore commissioning at the retort, then testing of the metal extraction system. Successful ore commissioning would allow practical completion to be declared before handover to the operations team.
Budget remains intact as operations team forms
The company says its forecast spend remains within the original A$6.1 million budget, with remaining expenditure tracking the forecasts outlined in its recent equity raising. The update follows the A$3.4m entitlement offer, which was reported as funding the Victorian demonstration plant through its targeted first magnesium production.
Operational preparation is also moving into its final phase. Latrobe says all key roles have been appointed, training has begun and the reagents required for a four-week operational campaign are on site. It also reports zero recordable incidents since the project began.
Final commissioning steps carry the delivery risk
The announcement is positive on installation and commissioning progress, but first metal remains a forward-looking target rather than an achieved result. Furnace heating, retort ore commissioning, metal extraction testing and practical completion all remain ahead, and the filing provides no production volume or confirmed quality data beyond the targeted crown specification.
Bottom Line?
The project has moved from construction into its decisive testing phase. The next meaningful evidence will be whether furnace heat-up and metal extraction produce consistent magnesium crowns before year-end without breaking the A$6.1 million budget.
Questions in the middle?
- Can furnace heating and retort commissioning be completed in time for the end-2026 first-metal target?
- What volume and consistency will the first magnesium crowns achieve once extraction testing begins?
- Will final commissioning expenditure remain within the A$6.1 million project budget during the operational campaign?
Sources
1-
Phase 1B Project 100% Installed (opens in a new tab)Official market announcement. Latrobe Magnesium Limited · 23 Nov 2026 · latrobemagnesium.com