Alchemy advances Valley Bore from drilling into mine evaluation
Alchemy Resources’ 40%-owned Valley Bore iron ore joint venture has approved a development evaluation program spanning resource estimation, mine planning and environmental work. Newcam Minerals will fund the phase, with a Mining Proposal targeted for June 2027.
- Mineral Resource Estimate targeted for early 2027
- Preliminary concept study expected to start in December 2026
- Alchemy retains a 40% interest free carried to a Decision to Mine
- Environmental and approvals work to build towards a June 2027 Mining Proposal
Add us as a preferred source on Google
Valley Bore enters development evaluation
Alchemy Resources Limited (ASX:ALY) is moving its Valley Bore iron ore project beyond first-pass exploration, with the Newcam-Alchemy Bryah Basin Iron Ore Joint Venture approving a work program designed to test whether the Western Australian project can support a potential mine development. The program combines a Mineral Resource Estimate, preliminary mine planning and environmental studies rather than adding another immediate round of exploration drilling.

The first major milestone is a preliminary concept study, targeted to begin in December 2026. It is expected to cover pit design, mine planning, production scheduling, high-level project economics and site requirements. The Mineral Resource Estimate is targeted for early 2027 and is intended to provide the technical foundation for pit optimisation and further development assessment. Neither study has yet been completed, and the announcement does not disclose project costs, production forecasts or economics.
Newcam funds the next project phase

The structure gives Alchemy exposure to the project without funding obligations through a Decision to Mine. Newcam Minerals holds 60% and is responsible for funding and advancing the project through the development evaluation phase, while Alchemy retains a 40% interest free carried to that decision point. The arrangement was formalised through a binding joint venture agreement in October, following Newcam’s exercise of its option to proceed.
That deal followed the placeholder and shifts the immediate burden of technical and economic work to Newcam. The joint venture may consider geotechnical drilling after the concept study, but that decision depends on the study’s outcomes and is not yet a committed program.
Environmental approvals enter the timetable
Environmental work is being advanced alongside the technical studies. Detailed Level 1 flora and fauna surveys began in November, building on desktop assessments and baseline studies. Topographical surveys and planning for surface water, soil and landform assessments are expected to begin in December, while waste-rock tonnage assessment and preliminary characterisation work are targeted for the first quarter of calendar 2027.
Alchemy is targeting environmental studies and native vegetation clearing permit submissions in the first or second quarter of 2027, followed by a Mining Proposal submission in June. Those dates are forward-looking targets, and the pathway remains dependent on the results of the resource and concept studies, further technical work and regulatory processes.
High-grade drilling now faces a conversion test

The development work builds on 15 reverse-circulation holes drilled for 1,027 metres at the Southern Ridge prospect in late 2025. Alchemy says the drilling outlined thick, continuous hematite zones from surface to at least about 50 metres vertically, with internal zones exceeding 63% to 66% iron on a calcined basis. Mineralisation remains open along strike and at depth, while mapped banded iron formation ridges extend across more than 2,000 metres.
The next question is whether those encouraging drill results can be converted into a defined resource and a credible mine concept. Until that work is delivered, Valley Bore remains a development opportunity with a structured timetable rather than an operating project.
Bottom Line?
The June 2027 Mining Proposal target gives Valley Bore a clear near-term catalyst, but the resource estimate and concept study must first establish whether the drilling can support an economic development case.
Questions in the middle?
- What tonnage and grade will the first Mineral Resource Estimate establish at Valley Bore?
- Will the concept study support further geotechnical drilling and a viable mine design?
- Can the joint venture meet its environmental submission and June 2027 Mining Proposal targets?
Sources