3 months added to Apollo Hill timeline as FID shifts to 2028
Saturn Metals says a four-week public review of Apollo Hill’s environmental approval application could add about three months to the project schedule, moving the planned Final Investment Decision from late 2027 to early 2028. The company will also delay its Definitive Feasibility Study to early 2027 while it assesses further engineering opportunities.
- Four-week EPA public review to precede further assessment
- Apollo Hill Final Investment Decision shifts to early 2028
- Definitive Feasibility Study delayed from next month to early 2027
- Additional information requests remain possible
- Engineering assurance work has identified optimisation opportunities
Add us as a preferred source on Google
EPA review adds three months to Apollo Hill schedule
Saturn Metals Limited (ASX:STN) now expects the planned Final Investment Decision for its Apollo Hill Gold Project in Western Australia to move from late 2027 into early 2028. The shift follows advice from the Environmental Protection Authority that Saturn’s environmental approval application will undergo a four-week period of public review.
The public comment period will be followed by an EPA assessment, with Saturn warning that the combined processes could add approximately three months to its development timeline. The process may also generate further requests for information, although the company said it believes the supplementary work likely to be required has already been commissioned or completed.
The permitting step comes after Saturn’s Apollo Hill mining lease was granted and its environmental review was submitted, according to the company’s October update. The latest announcement does not quantify any resulting change to project costs, capital requirements or operating assumptions.
DFS moves to early 2027 as optimisation work expands

Saturn will also push the release of its Definitive Feasibility Study from next month to early 2027. The delay follows financial model reviews, benchmarking and independent engineering peer reviews conducted as part of the company’s validation and assurance program.
Those activities have identified opportunities to further optimise Apollo Hill, and Saturn has elected to evaluate and incorporate the findings into the DFS. Managing Director Ian Bamborough said the additional time would allow “more comprehensive engineering and better integration” with the company’s emerging project execution plan (ASX:STN).
Saturn said the DFS delay is not expected to affect the revised development timeline. That leaves the permitting process as the immediate schedule variable: public submissions, any additional information requests and the EPA’s subsequent assessment could determine whether the early-2028 investment decision remains achievable.
Bottom Line?
The next meaningful test is whether the EPA review proceeds without further information demands, while the early-2027 DFS will show whether the optimisation work improves Apollo Hill’s project case without adding another delay.
Questions in the middle?
- Will the EPA public review generate additional information requests beyond Saturn’s existing preparation?
- What project improvements will emerge from the expanded DFS engineering and assurance work?
- Will the early-2028 Final Investment Decision remain achievable once the EPA assessment is complete?
Sources
1-
Apollo Hill Permitting and DFS Update (opens in a new tab)Verified company source. Saturn Metals Limited · 24 Nov 2026 · saturnmetals.com.au