Power Minerals has reported another high-grade rare earth intersection at its Morro do Ferro project in Brazil, including 54 metres at 5.08% TREO from surface. Mineralogical work also found bastnäsite accounted for about 87.5% of identified rare earth-hosting minerals, giving the company a clearer target for processing studies.
- 54m at 5.08% TREO and 0.83% MREO from surface in MFSR-059
- 4m at 12.62% TREO and 1.95% MREO from 15m
- A second 16m mineralised zone starts at 104m downhole
- Bastnäsite represented approximately 87.5% of identified REO-hosting minerals
- Maiden Mineral Resource Estimate targeted for year-end
MFSR-059 delivers another high-grade near-surface zone
Power Minerals Limited (ASX:PNN) has added another strong drill result to the emerging Morro do Ferro rare earths story, with hole MFSR-059 returning 54 metres at 5.08% TREO and 0.83% MREO from surface. Within that interval, the company reported 34.5 metres at 6.12% TREO and 1.01% MREO from 2.5 metres, including 4 metres at 12.62% TREO and 1.95% MREO from 15 metres.
The result came from Section SE-01, the first new section drilled southeast of Power’s earlier work. The company said the hole also produced a second 16-metre zone at 6,426 parts per million TREO from 104 metres, including 2 metres at 1.13% TREO from 112 metres. These are downhole intervals, so their true thickness has not yet been established.
The latest result extends a run of high-grade intersections at the Brazilian project, following the MFSR-057 drilling result, which included 111 metres at 8.25% TREO from surface. Power said the deeper zone in MFSR-059 may add to the area being assessed for resource definition because the current Exploration Target model did not include significant rare earth oxide mineralisation at that depth.
Bastnäsite result sharpens the processing question
Mineralogical testing provides a second strand to the announcement. Across 70 assay-validated samples from the project, GeoLabs Global found bastnäsite represented approximately 87.5% of the identified rare earth mineral mass, with cerianite accounting for 6.4% and monazite 6.1%. Bastnäsite was identified in every sample in that group.
That finding matters because Power is using established commercial processing experience with bastnäsite to guide its flowsheet work. The company has started bench-top testing and is collecting larger-diameter core in Brazil for expanded metallurgical studies, but it has not yet reported recovery rates or a completed process design. The company also said initial metallurgical work was expected to be completed this quarter.
Resource estimate remains the next hard test
Power is preparing a maiden Mineral Resource Estimate for Morro do Ferro by year-end, focused initially on the high-grade near-surface mineralisation. Drilling remains in progress, with assays still pending from numerous holes, while the company works to reconcile mineralogy with drillhole depth, weathering, lithology and grade.
The project’s high grades are becoming harder to dismiss as isolated results, but the announcement remains an exploration update rather than an economic assessment. Grade continuity, true geometry, recoveries, processing costs and the representativeness of the mineralogical samples will determine how much of the drilling can translate into a defined and potentially developable resource.
Bottom Line?
The next inflection point is not another spectacular interval alone, but whether the year-end resource estimate and metallurgical work convert repeated high grades into a coherent development case.
Questions in the middle?
- How much of the near-surface high-grade mineralisation will be included in the maiden Mineral Resource Estimate?
- Will metallurgical testing confirm that bastnäsite-dominant material can deliver commercially useful recoveries of the higher-value magnet rare earths?
- Does the deeper 16-metre zone represent a continuous addition to the deposit or a more localised occurrence?