WIN moves modular plant to Radio as gold restart takes shape

WIN Metals has completed the cash acquisition of a modular gravity processing plant for its proposed 120,000 tonnes per annum Radio Gold operation. The deal removes a previously planned share issue, but commissioning, approvals and project funding remain ahead.

  • $500,000 cash acquisition completed, plus a $50,000 option fee
  • No new WIN shares will be issued under the amended transaction
  • Plant is designed to support the proposed 120,000tpa Radio processing circuit
  • Previous metallurgical work recorded gravity gold recoveries of up to 87%
  • Equipment is being transported to the Radio Mine Site
An image related to Win Metals Ltd A photo of the logo for Win Metals Add us as a preferred source on Google
Image © middle. Logo © respective owner.

WIN Metals Ltd (ASX:WIN) has locked in a key piece of its proposed Radio Gold processing circuit, completing the acquisition of a modular gravity plant for $500,000 excluding GST. The equipment is now being moved to the Radio Mine Site, giving the company a tangible development milestone as it works towards a proposed 120,000 tonnes per annum operation.

Cash Deal Removes Planned Share Issue

The purchase price was originally structured as $250,000 in cash and $250,000 in WIN shares, but the company and Tungsten Mining NL (ASX:TGN) later agreed to convert the share component into cash. WIN has therefore paid $500,000 excluding GST on exercise of the option, in addition to the $50,000 option fee already paid, with no new shares to be issued.

That change means the previously proposed issue of up to 12.5 million WIN shares will not proceed. Tungsten Mining separately acquired $250,000 of WIN shares from an existing shareholder, so the transaction still involves a shareholding change outside the new-issue component, but does not add shares to WIN’s register under the plant purchase.

Plant Designed for Radio Throughput

Ball Mill frame, motor and Liquid resistance Starter
Image © Win Metals Ltd. From “Modular Gravity Plant on Its Way to Radio Gold Project”, 24 Nov 2026.

The modular gravity plant includes a run-of-mine bin, conveyors, scrubber trommel, 245kW ball mill, screen, spiral, jig and lamella thickener modules. WIN says the ball mill and plant design are suited to its proposed processing rate of 120,000 tonnes per year, or about 15 tonnes per hour, at the grind size identified in its Radio restart study.

Thickener components
Caption and image © Win Metals Ltd. From “Modular Gravity Plant on Its Way to Radio Gold Project”, 24 Nov 2026.

Previous metallurgical test work at Radio recorded gravity gold recoveries of up to 87%. The company says the plant was constructed in 2014, operated for about one month in a different tantalite-processing configuration and then remained idle before Tungsten Mining acquired it in 2017. WIN describes the equipment as being in excellent condition, although the announcement does not provide independent verification, a commissioning date or an updated capital and operating cost estimate.

Transport Marks Another Step Toward Restart

The acquisition follows Radio development approval, which covered the proposed open-pit and underground mine, processing infrastructure and a tailings dam lift, while Works Approval, funding and a final investment decision remained outstanding in that earlier update. WIN’s managing director and CEO Steve Norregaard said the plant purchase supports a “lean and mean” development strategy and can be integrated with infrastructure already at site (ASX:WIN).

The cash outlay also comes after the company reported an A$8.05m funding injection connected with its broader Radio restart position. The next test is less about acquiring equipment than turning it into an operating circuit: transport, installation, commissioning and demonstrated metallurgical performance will need to align with the proposed production case and any final funding decision.

Get ASX:WIN news the moment it breaks

Instant push notifications No waitlist Free
Download on the App Store iPhone & iPad
Get it on Google Play Android
Email alerts

Bottom Line?

The plant is now secured and moving to site, but Radio’s investment case still depends on installation, approvals, funding and successful commissioning.

Questions in the middle?

  • When will the modular plant be installed and commissioned at Radio?
  • Will commissioning confirm the proposed 120,000tpa throughput and earlier gravity recovery results?
  • What final funding requirement and development timetable will WIN present before making an investment decision?