DBI maps a path from steady income to a larger coal export terminal
Dalrymple Bay Infrastructure has confirmed its 7.155-cent Q3 distribution while outlining a possible 14.9Mtpa expansion that could lift terminal capacity to 99.1Mtpa. The income story is established; the growth story still depends on customer commitments, financing and a final investment decision.
- 7.155 cents per stapled security for Q3-26
- 20.655 cents in announced year-to-date distributions
- 28.62 cents of TY-26/27 distribution guidance maintained
- 8X expansion could add 14.9Mtpa at an estimated $1.583bn cost
- NECAP projects could add approximately $0.53/t to the terminal charge from July 2027
Add us as a preferred source on Google
Distribution guidance holds as expansion plans emerge
Dalrymple Bay Infrastructure Limited (ASX:DBI) has delivered the predictable part of its investment case: a 7.155-cent Q3-26 distribution and no change to its 28.62-cent TY-26/27 guidance. The more consequential detail arrived in the accompanying investor presentation, which put numbers around a possible expansion of its Dalrymple Bay Terminal from 84.2 million tonnes per annum to as much as 99.1Mtpa.

The Q3 payment takes announced year-to-date distributions in respect of FY-26 to 20.655 cents per stapled security. It comprises an unfranked dividend of 5.100 cents and a 2.055-cent partial repayment of the principal attached to each stapled loan note. DBI said the guided total represents a 5.3% yield based on its $5.43 closing security price on 24 November. The distribution has a 1 December record date and is due to be paid on 17 December, subject to the applicable approval process.
Terminal charge uplift is backed by approved capital works

DBI’s near-term revenue growth is tied less to a sudden change in coal throughput than to capital being added to the terminal’s regulated asset base. Its 84.2Mtpa capacity is fully contracted on a 100% take-or-pay basis to June 2028, with evergreen renewal options for customers, while the current pricing arrangement runs to 2031.
The company said $97.8 million of non-expansion capital expenditure, including $6.5 million of interest during construction, was added to the NECAP asset base on 1 July 2026. That lifted the Terminal Infrastructure Charge by $0.15 per tonne. A further approximately $300 million of direct capital expenditure and associated interest is expected to support an indicative additional uplift of about $0.53/t from 1 July 2027, assuming the stated interest-rate and commissioning assumptions. DBI’s presentation says every additional $0.10/t of the charge represents roughly $8.5 million of annual incremental revenue.

The figures build on the May distribution guidance uplift, when DBI forecast an 8.1% increase in the terminal charge and raised TY-26/27 distribution guidance to 28.62 cents. The latest presentation says the major Shiploader 1 replacement was completed on time and on budget at a budgeted cost of $165.4 million excluding interest, while the RL4 stacker-reclaimer replacement is expected to enter operations in January 2027.
8X offers a staged route to 99.1Mtpa
The longer-term option is the 8X project, a phased expansion wholly within the existing terminal footprint and supported by primary environmental approvals. DBI said the access queue represented approximately 35Mtpa of annualised demand as at 31 October, although that figure is not the same as a committed expansion order.

The initial phases described in the presentation would add 4.4Mtpa through a fourth shiploader on Berth 3, 4.1Mtpa through stockpile augmentation and 6.4Mtpa through new inloading systems. Together, the 14.9Mtpa program carries a front-end engineering and design estimate of $1.583 billion at a P95 confidence level, based on an assumed commencement date of 1 April 2028. DBI stressed that it retains discretion over how many phases, if any, proceed.
That distinction matters. The project requires commercial negotiations with access seekers, formal commitments to capacity, financing arrangements and a final investment decision. DBI also expects 8X capacity to carry a higher charge than the existing terminal infrastructure charge, reflecting the higher estimated cost per tonne of capacity. The current presentation therefore describes a substantial option rather than a committed construction program.
Income visibility meets coal-cycle and execution questions

For securityholders, the immediate proposition remains a contracted infrastructure asset with distributions tracking prior guidance and customer-approved capital works feeding future tariff revenue. The unresolved question is how much of the next phase of growth can be converted from presentation-slide optionality into contracted, financed investment without weakening that income profile.
Bottom Line?
DBI has visible near-term distribution support, but the larger valuation question rests on whether 8X demand becomes binding commitments rather than an access queue.
Questions in the middle?
- How much of the reported 35Mtpa access queue will convert into firm 8X capacity commitments?
- Will customer negotiations and financing support a final investment decision for one or more expansion phases?
- Can the planned NECAP additions deliver the projected tariff uplift without material cost or commissioning delays?