EQ Resources builds cash and advances tungsten growth plans
EQ Resources has entered FY2027 with $75.6 million in operating cash flow, $82.4 million of cash and production guidance of 240,000 to 280,000 metric tonne units. The recovery is gathering pace, but elevated injury rates and sizeable opposition to director option grants remain important investor watchpoints.
- $75.6 million of first-quarter FY2027 operating cash flow
- Cash increased to $82.4 million at 30 September from $28.2 million at 30 June
- FY2027 production guidance set at 240,000 to 280,000 metric tonne units
- Mt Carbine expansion remains on schedule for March-quarter 2027 commissioning
- Material opposition to remuneration report and director option resolutions
Add us as a preferred source on Google
Cash Generation Strengthens the Turnaround
EQ Resources Limited (ASX:EQR) is heading into its next growth phase with a considerably stronger financial base than it had at the start of FY2026. Chair Michael Nossal told shareholders that the company generated a record $75.6 million of operating cash flow in the first quarter of FY2027, while cash rose to $82.4 million at 30 September from $28.2 million at 30 June.
The operational figures are equally striking: production increased 81% quarter on quarter, prompting EQ Resources to issue full-year production guidance for the first time. The company is targeting 240,000 to 280,000 metric tonne units in FY2027, which Nossal said would be at least double the previous financial year's production. The update builds on the record FY2027 opening quarter, which had already delivered record revenue, EBITDA, profit and operating cash flow.
Mt Carbine Expansion Remains the Main Execution Test
The Mt Carbine expansion in North Queensland remains on schedule and on budget, with commissioning due in the March quarter of 2027. EQ Resources said ore stockpiles were being built ahead of the wet seasons, while resource and reserve drilling continued in Queensland and Spain. The project is central to the company's ambition to increase production while keeping its two existing mines operating reliably.
That growth agenda now extends beyond the current operations. In September, EQ Resources agreed to take a 10% interest in a joint venture with Elmet and Blue Moon Metals to restart the Springer APT plant in Nevada. The announcement does not disclose the financial terms of that investment, leaving the funding requirements and potential contribution of the venture unresolved.
Safety Concerns Temper Stronger Operating Results
The board's upbeat financial assessment came with a clear qualification. Nossal said injury rates were “simply too high” and that the company was undertaking independent audits at both sites, alongside new safety leadership at Mt Carbine. Management's actions will need to translate into measurable improvement as production rises, particularly while the company is adding expansion work to an already demanding operating environment.
The chair also pointed to tungsten's importance in industrial manufacturing, computing, semiconductors, aerospace, medical technologies, energy and defence, as well as the concentration of global supply in a small number of countries. EQ Resources operates mines in Australia and Spain and described its position as a rare opportunity, but the filing places the emphasis on disciplined execution rather than simply higher prices.
Proxy Votes Support Board While Option Grants Draw Opposition
Preliminary direct and proxy voting supported all 11 resolutions, although the level of opposition was not uniform. The remuneration report recorded 142.9 million votes against, while the proposed option grants for Chair Michael Nossal and director Nicole Brook each attracted about 940 million votes against, roughly 35% of votes recorded on those resolutions. The proposed increase in the aggregate non-executive director fee pool also drew 185.9 million votes against.
The figures are not final AGM results: the company said the completed outcome would be communicated after the meeting. For investors, the more consequential test now shifts from the proxy table to delivery: whether cash generation can be sustained, Mt Carbine can be commissioned on schedule, and safety performance improves without disrupting the production ramp.
Bottom Line?
The turnaround now has cash and production momentum behind it, but FY2027 will test whether EQ Resources can convert that momentum into safe, repeatable delivery.
Questions in the middle?
- Can production remain within the 240,000 to 280,000 metric tonne unit FY2027 guidance as the company manages seasonal conditions and expansion work?
- Will the Mt Carbine expansion reach commissioning in the March quarter of 2027 without pressure on cash or operating performance?
- How quickly will the independent safety audits and new site leadership produce measurable improvement in injury rates?