Marimaca Copper has secured Sprott investment committee approval for a proposed US$450 million package to develop its Marimaca Oxide Deposit in Chile. The milestone reduces a major funding hurdle, but the money remains subject to due diligence, binding documents, financial close and a Final Investment Decision.
- Proposed US$425 million senior secured facility plus US$25 million equity investment
- Initial US$100 million drawdown conditional on FID and other requirements
- 7.5-year facility with interest at 5.75% plus the greater of SOFR and 2.75%
- Funding remains subject to definitive documentation and financial close
- Pampa Medina is carved out from the facility’s security and guarantor package
Sprott approves proposed US$450 million development package
Marimaca Copper Corp. (TSX:MARI, ASX:MC2) has cleared a significant financing milestone for its flagship Chilean copper project, receiving investment committee approval from Sprott for a proposed US$450 million package. The package combines up to a US$425 million senior secured project finance facility with up to US$25 million of equity investment in Marimaca.
The approval is not financial close. Sprott still has to complete legal and financial due diligence, while the parties must negotiate definitive documents and satisfy customary conditions before funds can be drawn. The arrangement is based on a non-binding term sheet, leaving open the possibility that the package may not complete on the terms currently contemplated, or at all.
US$100 million first draw depends on FID
Subject to a Final Investment Decision and other conditions, the first US$100 million would be released to Marimaca. Further advances would become available as the company satisfies additional conditions, with the facility intended to cover construction and ramp-up costs, working capital, financing costs and general corporate purposes.
The proposed debt has a 7.5-year term and carries a floating interest rate of 5.75% a year plus the greater of SOFR and 2.75%. Marimaca may capitalise 85% of interest costs until the availability period ends. Principal repayments are scheduled to begin on March 31, 2031, with quarterly repayments equal to 4% of outstanding principal, including capitalised interest and other costs, and the remaining balance due at maturity.
Funding supports MOD while preserving Pampa Medina flexibility
The facility would not require hedging, cash sweeps, production-linked payments or the issue of additional equity under the stated terms. It would be secured against the assets of the borrower and guarantors, but Pampa Medina and its related subsidiaries would be carved out of the security and guarantor package. That structure is notable because Marimaca has recently reported fresh Pampa Medina drilling, including a 102-metre intersection grading 1.00% copper and an 8-metre interval grading 3.21% copper.
The company said the financing allows it to continue advancing Pampa Medina at its desired pace while constructing the Marimaca Oxide Deposit. It also arrives after Marimaca reported US$126.6 million in cash at September 30 and said further funding would be needed to advance the project beyond the next 12 months, making the proposed package a potentially important bridge from exploration-stage balance sheet strength to construction financing.
Construction financing still has several gates to clear
Marimaca said detailed engineering, site activity and construction preparation are expected to accelerate through the coming months, with critical-path items scheduled to continue through 2026 and 2027. But the next hard evidence will be less about the headline commitment than the execution: definitive financing documents, completion of the broader construction funding package, satisfaction of conditions precedent, financial close and the company’s formal FID.
Bottom Line?
Sprott approval materially improves Marimaca’s proposed funding pathway, but construction financing is not secured until documentation, conditions and FID are completed.
Questions in the middle?
- Will Sprott’s due diligence and definitive documentation preserve the proposed US$425 million facility and US$25 million equity investment?
- What additional funding, if any, will Marimaca require to complete the broader construction financing package?
- When will the company reach FID and trigger the proposed initial US$100 million drawdown?