TMK Energy Finds Fresh Evidence as Gurvantes LF-08 Drilling Nears

Energy By Maxwell Dee 4 min read

TMK Energy says its Gurvantes pilot remains on schedule, with two wells re-completed and LF-08 ready to drill. A pressure test at LF-02 produced further evidence that reservoir pressure is nearing the level needed to release gas from the coal seams, although the commercial payoff remains unproven.

  • LF-02 and LF-03 successfully re-completed with smaller fit-for-purpose pumps
  • LF-02 produced about 25,200 standard cubic feet of gas during a 14-day shut-in
  • LF-08 drilling expected to begin this week and finish within about two weeks
  • Initial LF-02 restart rate briefly reached 14.4 Mscf/d before returning to earlier levels
  • LF-06 remains the final well scheduled for re-completion in 2026

LF-02 Pressure Test Strengthens Desorption Case

TMK Energy Limited (ASX:TMK) has reported a useful technical milestone at its 100%-owned Gurvantes XXXV Pilot Well Project, but not yet a commercial one. LF-02 continued producing gas during a 14-day shut-in with its pump switched off, generating approximately 25,200 standard cubic feet while bottomhole pressure stabilised near the company’s interpreted desorption pressure.

The test also showed the reservoir pressure had fallen further, in line with earlier modelling. Pressure rose to about 1,269 kPa at the top of the coal and remained stable during the final seven days, which TMK interprets as being at or close to desorption pressure at the LF-02 location. In coal seam gas, that distinction matters: the company is seeking evidence that falling pressure is allowing gas to come out of the coal and flow into the well.

Re-completed Wells Return to Production

LF-02 and LF-03 have now been re-completed with optimised wellbores, smaller casing and smaller fit-for-purpose downhole pumps. Both wells restarted successfully, confirming the equipment is mechanically operating and able to bring water and gas to surface.

LF-02 initially produced about 14.4 Mscf/d after restart, nearly three times its pre-workover rate of roughly 5 Mscf/d, before easing back to the earlier level the following day as the water column was drawn down. TMK attributes the short-lived surge to free gas accumulated around the wellbore during the shut-in, rather than presenting it as a sustained production improvement. The longer-term value of the re-completion will therefore be determined over the coming months.

LF-08 Drilling Set to Test the Next Step

“Drilling rig ready to commence operations at LF-08.”Caption and image © TMK Energy Limited. From “2026 Work Program Update”, 25 Nov 2026.

The next material test is LF-08, the only new pilot well in the 2026 program. The rig arrived on site on 3 November and has been rigged up, with the conductor already set. Drilling is expected to begin this week once senior crew become available from the contractor’s other project in Mongolia, with completion expected within two weeks of commencement and production to follow shortly afterwards.

LF-08 was already identified as the next major field activity in TMK’s LF-08 drilling plan, and its results are expected to guide the company’s 2027 appraisal planning. LF-02 will be shut in while LF-08 is drilled to reduce the risk of reservoir damage to either well.

Commerciality Still Depends on Sustained Results

TMK says it remains fully funded for the 2026 work program and is targeting a commerciality assessment this year, followed by an appraisal period in 2027. That target is not the same as a commerciality decision: the announcement provides no reserves upgrade, production forecast or quantified economic result.

The immediate evidence is encouraging but uneven. Pressure behaviour at LF-02 supports the desorption thesis, while the initial post-restart gas flush quickly returned to pre-workover rates. The market’s next hard data points are likely to be LF-08’s drilling and production results, and whether the re-completed wells deliver a durable improvement rather than a brief response to intervention.

Bottom Line?

LF-08 should provide the next important test of the Gurvantes model, while sustained output from the re-completed wells will determine whether the technical progress translates into commercial evidence.

Questions in the middle?

  • Will LF-08 encounter reservoir conditions consistent with the pressure and desorption behaviour observed at LF-02?
  • Can LF-02 and LF-03 sustain higher gas production after their initial post-restart responses fade?
  • What reserves, development and funding conclusions will TMK draw when the 2027 appraisal program is finalised?