Canyon Resources has withdrawn the Minim Martap project’s feasibility study outcomes, production targets, financial forecasts and Ore Reserves after funding delays made the planned rail-led ramp-up unachievable. The company is seeking up to A$70.1 million to reach a conditional June 2027 first shipment, while warning that further funding will be needed soon after.
- DFS outcomes, production targets and Ore Reserves withdrawn
- A$70.1 million one-for-one entitlement offer at A$0.034
- June 2027 first shipment target requires at least A$48 million
- Existing rail fleet capacity is approximately 35,000 tonnes per month
- Further A$29.5 million minimum funding identified for late 2027
Minim Martap Feasibility Study Withdrawn
Canyon Resources Limited (ASX:CAY) has discarded the numbers underpinning its Minim Martap development plan, withdrawing the project’s Definitive Feasibility Study outcomes, production targets, financial forecasts and Ore Reserves. The decision follows funding delays that stopped planned investment in rail infrastructure and additional rolling stock, leaving the company unable to deliver the production schedule previously presented to investors.
The reset follows an earlier AFG funding review, which had already seen the lender suspend further drawdowns from Canyon’s Cameroon project facility. Canyon now expects to remain substantially reliant on its existing rolling stock fleet for at least three years, with the resulting constraints described as a material departure from the DFS assumptions.
A$70.1 Million Raise Targets June Shipment
Canyon is seeking up to approximately A$70.1 million through a non-underwritten, renounceable one-for-one entitlement offer priced at A$0.034 per share. The offer price is a 10.5% discount to the company’s 20 November closing price of A$0.038. At least approximately A$48 million needs to be raised, according to Canyon, for the remaining development work required to target a first bauxite shipment in June 2027.
The money is earmarked for final locomotive and wagon payments, mine and Inland Rail Facility work, commissioning, port infrastructure and dredging, community compensation, operating costs to first shipment and working capital. It does not fund Stage 2 expansion or AFG debt service. Shareholders who do not take up or sell their entitlements will be diluted if new shares are issued, while the entitlement offer itself can be withdrawn if the board considers subscriptions insufficient to protect short-term solvency.
Rail Capacity Replaces Production Guidance
Canyon’s existing fleet has estimated transport capacity of approximately 35,000 tonnes a month, but the company stresses that this is a rail-capacity statement, not a production target. Seven locomotives have arrived in Douala and 140 of 160 ordered wagons have been delivered, with commissioning, testing and operator training still under way. Mining is scheduled to begin in the first quarter of 2027, subject to village compensation payments and other conditions.
Port economics remain unresolved. Canyon is assessing Panamax, Supramax and Capesize options, alongside the required dredging and transhipping arrangements, and has not confirmed a preferred configuration or definitive timetable. The lower initial volumes associated with the Stage 1 fleet may limit access to the freight assumptions used in the earlier development case.
Funding Gap Extends Beyond First Shipment
As at 31 October, Canyon held approximately A$24.3 million in cash, including A$4.3 million of restricted cash, and had drawn approximately US$75 million of a US$140 million AFG facility. AFG’s further drawdowns remain suspended pending a lender review and site visit expected in December, with no forecast from Canyon on whether or when funding access will resume.
Even if the entitlement offer reaches its maximum, Canyon estimates it will require at least a further A$21 million from July to December 2027, plus A$8.5 million for AFG debt service between October and December. The company has warned that if sufficient funding is not secured, it may need to consider project deferral, re-scoping, restructuring or, in the most serious scenario disclosed, voluntary administration.
Mineral Resource Survives Without an Ore Reserve
The previously reported Mineral Resource remains unchanged after Canyon and SRK concluded that its underlying assumptions and reasonable prospects for eventual economic extraction remain valid. That is a narrower statement than economic feasibility: Canyon has not established a replacement development pathway, production forecast or Ore Reserve, and says any restatement would require a new JORC-compliant study after initial operating evidence is available.
The company expects that technical and economic assessment to occur during 2027, subject to funding. Initial operations are intended to test product quality, customer acceptance, mine and logistics performance, actual costs and working capital requirements. Those shipments, Canyon says, would not by themselves demonstrate economic viability at a larger scale.
Control and Capital Structure Risks
The entitlement offer could double Canyon’s issued shares from approximately 2.06 billion to 4.12 billion if fully subscribed. The A2MP Parties, which currently hold 55.56% of Canyon, have not committed to participate. If they subscribe for their full entitlement while other shareholders do not, their voting power could rise to approximately 71.44%, although the company has made no forecast about their participation or future funding support.
The offer opens on 4 December and is scheduled to close on 16 December 2026, with entitlement trading expected to end on 9 December. The immediate test is therefore not simply whether Canyon can finance construction to June, but whether it can raise enough capital to reach a first shipment without relying on forecasts it has now withdrawn.
Bottom Line?
Canyon has exchanged a defined development case for a funding-dependent trial phase. The critical evidence will be the capital raised, AFG’s response and whether the mine-to-port chain can operate economically at constrained rail volumes.
Questions in the middle?
- Can the non-underwritten offer raise the approximately A$48 million Canyon says is needed for first shipment?
- Will AFG restore drawdowns after its December review and site visit?
- Can initial operations generate enough cost, freight and customer evidence to support a replacement Ore Reserve and viable 2027 development case?