Strike’s South Erregulla plant crosses into revenue testing

Strike Energy has connected its $187 million South Erregulla Power Plant to Western Australia’s grid, moving the project into AEMO testing before targeted commercial operations in late January 2027. The plant is expected to combine contracted Capacity Credit revenue with electricity sales, although final commissioning still stands between energisation and full operations.

  • 85 MW South Erregulla plant connected to the SWIS
  • AEMO hold-point testing expected to take six to eight weeks
  • $187 million invested, $50 million above the original FID estimate
  • Capacity Year 2029 revenue illustration of $39 million from Capacity Credits
  • Commercial operations targeted for late January 2027
An image related to Strike Energy Limited A photo of the logo for Strike Energy Add us as a preferred source on Google
Image © middle. Logo © respective owner.

South Erregulla reaches grid energisation

Strike Energy Limited (ASX:STX) has energised and connected its 85 MW South Erregulla Power Plant to Western Australia’s South West Interconnected System, taking its largest growth investment from construction into commissioning. Energisation was completed on 20 November in conjunction with Western Power.

Schematic representation of South Erregulla Power Plant and associated infrastructure
Caption and image © Strike Energy Limited. From “South Erregulla Power Plant Update”, 26 Nov 2026.

The milestone begins AEMO hold-point testing, which is expected to take six to eight weeks. Output will be increased progressively from 10 MW to the plant’s full 85 MW nameplate capacity, with AEMO and Western Power required to approve each stage before the facility advances. Strike is targeting commercial operations in late January 2027, subject to that process.

Testing can generate early electricity revenue

The testing phase is not entirely revenue-free. As the 20 Jenbacher gas engines ramp up, electricity dispatched into the grid can earn prevailing spot prices in Western Australia’s Wholesale Energy Market. That provides an initial commercial link for the plant, but the company’s full operating milestone remains contingent on successful technical testing and approvals.

The project had been approaching this point in recent months, with Strike’s scheduled November energisation bringing the facility to the threshold of revenue generation. The plant is designed as fast-start, flexible generation for a system facing the progressive retirement of State-owned coal-fired capacity by 2030.

Final project cost rises to $187 million

Strike says total investment has reached a final forecast $187 million, excluding capitalised interest. That includes $153 million for the power plant, $32 million for grid connection infrastructure and $2 million for operational readiness. About $9 million of the total is allocated to commissioning, close-out work, owners’ team costs, operational readiness and a Western Power transfer charge before first commercial cash flows.

The figure is approximately $48 million above the $137 million sanctioned at final investment decision in November 2024, excluding operational readiness. Strike attributes the increase primarily to the expanded scope of Western Power’s transmission and network connection works, as well as upstream and well workover activity, engineering costs, inflation and project delays.

Capacity revenue underpins the operating case

Strike says South Erregulla has secured Capacity Credits through Western Australia’s Reserve Capacity Mechanism through Capacity Year 2029. For the 2029 year, running from 1 October to 30 September, the company illustrates approximately $39 million of annual Capacity Credit revenue, alongside an additional $36 million to $42 million from electricity sales.

Those electricity figures are illustrative rather than guaranteed outcomes, and depend on market conditions and dispatch. Strike expects the plant’s direct access to gas from its wholly owned South Erregulla field to provide operating-margin benefits, but the next hard test is whether commissioning proceeds to commercial operation on the targeted timetable.

Operations leadership added for next phase

Strike has appointed Ragan Stonier as Chief Operating Officer as the company shifts towards operating the facility. Stonier brings more than 30 years of energy-sector experience spanning operations, project delivery and asset management, according to the announcement.

Get ASX:STX news the moment it breaks

Instant push notifications No waitlist Free
Download on the App Store iPhone & iPad
Get it on Google Play Android
Email alerts

Bottom Line?

The construction milestone is significant, but the investment case now turns on AEMO approvals, the remaining commissioning spend and whether the plant reaches commercial operations in late January 2027.

Questions in the middle?

  • Will AEMO and Western Power approve each hold point without extending the six-to-eight-week testing window?
  • How will the final $187 million project cost affect realised returns once commercial cash flows begin?
  • What level of electricity sales and operating margin will South Erregulla deliver beyond its contracted Capacity Credit revenue?

Sources

1