Alliance Nickel Finds a Potentially Cheaper Route for NiWest

Mining By Maxwell Dee 4 min read

Alliance Nickel is testing a vat-leaching flowsheet that could remove much of NiWest’s A$1.6 billion water infrastructure requirement while lifting recovery above the 2024 DFS benchmark. The potential upgrade remains unproven, with Phase 2 results due by the end of 2026.

  • Vat leaching could replace more than 200 kilometres of planned water infrastructure
  • Potential recovery above the DFS benchmark of 78% nickel
  • Phase 2 testwork is underway across broader ore types and operating conditions
  • Any capital or operating savings remain subject to testwork and a revised study
  • Strategic investor discussions remain incomplete and may not produce a transaction

Vat Leaching Targets NiWest’s Largest Capital Item

Alliance Nickel Limited (ASX:AXN) has identified a potentially substantial way to reshape the NiWest nickel-cobalt project: change how acid contacts the ore, rather than replace the atmospheric leaching concept altogether. The proposed vat-leach route could remove much of the water system included in the 2024 definitive feasibility study, including more than 200 kilometres of pipeline and about A$310 million of water infrastructure.

“Proposed NiWest Ni-Co Project”Caption and image © Alliance Nickel Limited. From “Managing Director's AGM Presentation”, 26 Nov 2026.

That is a target, not a booked saving. NiWest’s existing DFS carries all-in development capital of about A$1.6 billion, including contingency, alongside a post-tax net present value of about A$1.5 billion. Alliance says the alternative flowsheet could reduce that capital burden, but it has not yet released revised project economics.

Phase 2 Testwork Will Put Numbers Behind the Proposal

“Acid only leaches the ore it actually contacts.”Caption and image © Alliance Nickel Limited. From “Managing Director's AGM Presentation”, 26 Nov 2026.

The case for vat leaching rests on a relatively simple proposition: a heap relies on time and irrigation to contact the mineral, while a flooded vat could expose more of the ore to acid more quickly. Alliance says the 2024 DFS assumed a 105-day irrigation period within an approximately 18-week module cycle, with steady-state nickel recovery of 78% to product.

The company’s Phase 1 vat-leach results were described as encouraging and supported a second testing phase. That work is now examining vat conditions, acid consumption and ore variability across a wider selection of Mt Kilkenny material, with completion targeted for the end of the fourth quarter. The presentation says the results will determine whether the project can move to large-scale pilot work and an updated feasibility study.

Recovery, Water and Cycle Time Remain Unquantified

Alliance is pitching four potential benefits from the same processing change: lower capital, higher nickel and cobalt extraction, a shorter leach cycle and reduced water consumption. The company argues that a vat’s smaller exposed surface could also reduce evaporation losses in the Goldfields climate, potentially making local water sources sufficient and removing the need for the regional pipeline system contemplated in the DFS.

Those benefits still depend on metallurgy and engineering. The presentation does not provide final recovery figures, a confirmed cycle time, revised operating costs or a replacement capital estimate. It also cautions that the production target is underpinned 99% by Probable Ore Reserves and 1% by Inferred Mineral Resources, with the latter carrying low geological confidence.

Funding Plans Still Depend on a Smaller Project

Alliance says it continues to see several potential funding sources for NiWest, including project debt, export credit support, equity and strategic investors. Export Finance Australia’s letter of support remains conditional and non-binding, while discussions with strategic investors are incomplete and may not result in a transaction.

A lower capital requirement would improve the arithmetic of that funding mix, but the company acknowledges that finance is not assured and could be available only on terms that dilute existing shareholders or otherwise affect their value. The immediate catalyst is therefore not a financing announcement, but the Phase 2 data that must establish whether vat leaching can deliver the capital and recovery claims now being tested.

Bottom Line?

The opportunity is potentially large because water infrastructure is a major part of NiWest’s DFS capital, but the investment case still turns on Phase 2 metallurgy and a revised feasibility study.

Questions in the middle?

  • Will Phase 2 testing confirm recovery above the DFS benchmark across a representative range of NiWest ore?
  • How much of the planned A$310 million water infrastructure can actually be removed after engineering and permitting work?
  • Can Alliance secure strategic or project finance before the funding requirement and shareholder dilution risk become more pressing?