Minerals 260 has ordered the major mills and crusher for its 6.2Moz Bullabulling gold project, moving the development from study work towards construction. Village works, water infrastructure and grade-control drilling are also advancing, although the project still requires a completed DFS, remaining approvals and a positive investment decision.
- CITIC to supply SAG and ball mills; Metso to supply primary crusher
- Village construction is more than 50% complete and targeted for Q1 CY2027 operation
- 70,000m grade-control drilling program has commenced
- Initial 26,000m program reconciled to within 1% of contained gold
- DFS and Final Investment Decision remain targeted for Q1 CY2027
Bullabulling Equipment Orders Mark a Construction Milestone
Minerals 260 Limited (ASX:MI6) has placed orders for the long-lead processing equipment at its 100%-owned Bullabulling Gold Project in Western Australia, a step that puts physical procurement alongside the company’s feasibility and approvals work. CITIC Heavy Industries will supply the SAG and ball mills, while Metso Corporation will provide the primary crusher after a competitive tender process and inspections of manufacturing facilities in China.
The CITIC agreement also gives Minerals 260 access to an Intelligent Grinding Expert System. The company says the platform will provide real-time mill condition monitoring, online particle-size measurement and fault diagnostics, supporting mill operation and condition-based maintenance. The announcement does not disclose the value of the equipment orders or provide an updated project capital cost.
Village and Water Works Advance Ahead of Major Construction
More than half of the project village has been built, with the facility still scheduled to be operational in the first quarter of calendar 2027. That timing is intended to support major construction activities after a targeted Final Investment Decision in the same quarter. The development is also backed by recent Bullabulling debt funding, which the company previously said had reached credit-approved commitments but had not yet reached financial close.
Water infrastructure is progressing in parallel: 24 bores have been installed, with test pumping and modelling under way. Minerals 260 has expanded water exploration to support its stated 7.5 million tonnes per annum production goal. That target needs careful reading, however. The company’s pre-feasibility study is based on a 5Mtpa operation, while the 7.5Mtpa pathway remains subject to further expansion studies and has not yet been established as economically or technically viable.
Grade Control Supports Early Mine Planning
Minerals 260 has completed its analysis of an initial 26,000-metre grade-control program. The resulting model reconciled to within plus or minus 1% of contained gold for the area drilled against the 6.2Moz Mineral Resource Estimate. This is a result for the drilled area, rather than a revised resource or a guarantee about future production.
A further 70,000m program has now started, using 10m by 10m drill spacing and designed to reduce uncertainty around the first nine months of production. The work builds on the company’s initial Bullabulling grade control, which reported results consistent with the existing resource model while identifying higher-grade zones at Phoenix and Bacchus.
DFS and Approvals Still Gate the Investment Decision
The Definitive Feasibility Study remains scheduled for completion in the first quarter of 2027 and is expected to include the pathway towards 7.5Mtpa. Remaining approvals are progressing through Western Australia’s state approvals process and are described as being on track to support the planned FID. The company says Bullabulling is fully funded through to first production, but the announcement also retains the usual conditions around approvals, financing access, construction, commissioning and other forward-looking assumptions.
For shareholders, the next test is whether procurement, water supply, grade-control results and permitting can converge into a financeable development plan on the stated timetable. Ordering equipment reduces one element of future execution risk, but it does not remove the larger decisions still due in Q1 CY2027: the completed DFS, remaining approvals and the FID itself.
Bottom Line?
The equipment orders make Bullabulling look more like a project moving into execution, but the investment case still turns on the Q1 CY2027 DFS, approvals and FID.
Questions in the middle?
- Will the DFS retain the 5Mtpa Stage 1 basis or establish a credible and economic pathway to 7.5Mtpa?
- Can water exploration and modelling support the planned production rate without changing project costs or timing?
- Will the remaining approvals and financing conditions be completed in time for the targeted Q1 CY2027 FID?