Minerals 260 moves Bullabulling closer to construction with mill orders

8:22am on Friday 27th of November, 2026 AEDT • Mining
Read Story

Minerals 260 moves Bullabulling closer to construction with mill orders

8:22am on Friday 27th of November, 2026 AEDT
Key Points
  • CITIC to supply SAG and ball mills; Metso to supply primary crusher
  • Village construction is more than 50% complete and targeted for Q1 CY2027 operation
  • 70,000m grade-control drilling program has commenced
  • Initial 26,000m program reconciled to within 1% of contained gold