Minerals 260 moves Bullabulling closer to construction with mill orders
8:22am on Friday 27th of November, 2026 AEDT
•
Mining
Read Story
Minerals 260 moves Bullabulling closer to construction with mill orders
8:22am on Friday 27th of November, 2026 AEDT
Key Points
CITIC to supply SAG and ball mills; Metso to supply primary crusher
Village construction is more than 50% complete and targeted for Q1 CY2027 operation
70,000m grade-control drilling program has commenced
Initial 26,000m program reconciled to within 1% of contained gold