Home › Mining › Element 25 (ASX:E25)

Element 25 pushes Butcherbird toward 1.1Mtpa production

Mining By Maxwell Dee 6 min read

Element 25 has completed early works and advanced procurement for the A$64.8 million expansion of its Butcherbird manganese project, targeting 1.1 million tonnes a year of concentrate and mechanical completion in 2027. The strategy is gaining physical momentum, but NAIF financial close and the financing of its Louisiana refining project remain unresolved.

  • Butcherbird expansion targets 1.1Mtpa of manganese concentrate
  • Early works completed and major equipment procurement advanced
  • A$64.8 million capital cost, with stated pre-tax NPV of A$561 million
  • NAIF financial close remains pending
  • Louisiana HPMSM project retains US$166 million grant support but still requires financing and permitting

Butcherbird moves from preparation into construction

Element 25 Limited (ASX:E25) is presenting its Butcherbird expansion as a construction-ready project with the groundwork largely in place, but the company still needs to clear the financing gate before the main build can fully proceed. The Western Australian manganese operation is being expanded to produce 1.1 million tonnes a year of concentrate, with mechanical completion targeted for 2027.

“Early Works Package Completed”Caption and image © Element 25 Limited. From “AGM Presentation”, 27 Nov 2026.

The early works package is described as complete. It includes site clearing, bulk earthworks, a reclaim tunnel, process-water storage and pipelines, an upgraded operations centre, and core power, communications, water and wastewater services. Detailed engineering and issued-for-construction packages are complete, while long-lead equipment including a mineral sizer, logwasher, conveyors and feed-hopper components has entered fabrication, delivery or inspection.

“Early works package (SP1)”Caption and image © Element 25 Limited. From “AGM Presentation”, 27 Nov 2026.

That places the project materially further along than a feasibility-stage development. Element 25 says its construction contract has been finalised subject to financial close, with mining, haulage, port and offtake arrangements also progressed. The company’s Butcherbird early works were reported as materially complete in October, and the latest presentation now points to the transition into the main construction phase.

Expansion economics rest on a modest capital bill

The project’s stated economics are substantial relative to the proposed construction spend. Element 25 lists capital cost at A$64.8 million, a real pre-tax NPV8 of A$561 million and a pre-tax internal rate of return of 96%. The feasibility case assumes 6.1 million tonnes of ore mined annually, 1.1 million tonnes of concentrate production, a 31.6% manganese concentrate grade and an 18.3-year mine life.

“Large, Long-Life Manganese Mine in the Pilbara.”Caption and image © Element 25 Limited. From “AGM Presentation”, 27 Nov 2026.

Those figures are company estimates rather than fresh independent analysis in the AGM presentation. They also depend on the underlying production, pricing, operating and funding assumptions continuing to hold. The stated reserve is 101.4 million tonnes at 10.4% manganese, within a broader 274 million tonne resource grading 10.0%, giving Element 25 room to point to longer-term resource potential beyond the current reserve case.

NAIF close remains the immediate execution hurdle

The Northern Australia Infrastructure Facility has approved finance of up to A$50 million, but contractual and financial close remain pending. That unresolved step matters because the construction contract is conditional on financial close, even as site works and equipment procurement move ahead.

Element 25 has also arranged a A$30 million standby ATM facility with Acuity Capital and completed an A$18 million placement at A$0.30 during the timeline shown in the presentation. These funding measures sit alongside the proposed NAIF facility, but the presentation does not provide a complete funding bridge for the expansion or confirm that all remaining conditions have been satisfied.

Louisiana strategy retains ambition and uncertainty

“Planned HPMSM facility in Louisiana, USA”Caption and image © Element 25 Limited. From “AGM Presentation”, 27 Nov 2026.

The second leg of the strategy is a planned Louisiana facility producing 65,000 tonnes a year of high-purity manganese sulphate monohydrate, or HPMSM, for battery markets. Element 25 highlights a US$166 million Department of Energy grant and partnerships involving Stellantis and General Motors, while also making clear that the facility remains subject to successful project financing and permitting.

“Project timing driven by three intersecting elements.”Caption and image © Element 25 Limited. From “AGM Presentation”, 27 Nov 2026.

That commercial picture is not static: the Louisiana project reset previously covered the termination of existing GM agreements and unfinished definitive Stellantis documentation. The AGM presentation therefore sets out a sizeable strategic opportunity, but not yet a fully funded or permitted processing operation.

Element 25’s broader pitch is that Australian manganese concentrate can feed a non-China HPMSM supply chain as demand grows for higher-manganese battery chemistries. The presentation cites the concentration of HPMSM refining in China and positions its proprietary process as lower-waste and less reliant on toxic reagents, although the commercial value of that proposition will depend on financing, permitting, construction and customer commitments rather than the strategy alone.

The next milestone is financial close

“Equipment Fabrication and Procurement Advanced”Caption and image © Element 25 Limited. From “AGM Presentation”, 27 Nov 2026.

The company has supplied investors with a clearer execution map: finish the funding process, award and mobilise the main construction package, continue equipment delivery and work towards mechanical completion in 2027. The immediate question is whether the project can convert its construction-ready status into funded construction without weakening the economics or requiring additional shareholder support.

Bottom Line?

Butcherbird is physically advancing, but NAIF financial close and the funding of Louisiana will determine whether Element 25’s global manganese plan becomes an operating business rather than an ambitious project pipeline.

Questions in the middle?

  • When will NAIF financial close be completed, and what conditions remain outstanding?
  • What funding mix will support Butcherbird construction alongside the company’s other commitments?
  • Can the Louisiana facility secure definitive customer arrangements, financing and permits after the reset of its GM and Stellantis framework?

Sources