Galan Lithium’s Hombre Muerto West Nears Production with Nano-Filtration Plant En Route
Galan Lithium advances its Hombre Muerto West project with key infrastructure in transit and construction progressing ahead of schedule, targeting lithium chloride production in the first half of 2026.
- Nano-filtration plant assembled, tested, and now shipping to site
- Evaporation ponds redesigned and liners installed to support Phase 1 output
- Phase 1 construction on track for lithium chloride production in H1 2026
- Potential expansion of Phase 1 production capacity under evaluation
- Project remains within budget and aligned with development timeline
Progress on Critical Infrastructure
Galan Lithium Limited (ASX – GLN) has reported significant strides in the development of its Hombre Muerto West (HMW) lithium project in Argentina. The company has completed assembly and pre-installation testing of its nano-filtration plant in Sydney, a vital component for lithium chloride production. This plant is now en route to South America, with commissioning expected to begin shortly after arrival in early 2026.
Site Developments and Production Readiness
On-site, Galan has made notable progress with the redesign and scaling of evaporation ponds 4 and 5 to support the Phase 1 production target of 4,000 tonnes per annum of lithium carbonate equivalent (LCE). Liner installations for these ponds are complete, and subdivision work is underway to optimize lithium concentration. Additionally, earthworks and concrete foundations for the processing plant have been finalized, with procurement of key infrastructure such as power and pumping systems advancing in line with the project schedule.
On Track and Exploring Expansion
The company remains confident in delivering Phase 1 within budget and on schedule, aiming for first lithium chloride production in the first half of 2026. Encouragingly, Galan is also assessing the feasibility of increasing Phase 1 production capacity from the current 4,000 tpa LCE to approximately 5,400 tpa LCE, as outlined in its 2023 Definitive Feasibility Study. This potential expansion could enhance the project’s output and strengthen its position in the lithium market.
Strategic Positioning in the Lithium Triangle
HMW is one of the world’s top lithium brine projects, distinguished by its large, high-purity mineral resource and low-cost production profile. Situated in Argentina’s lithium triangle, the project benefits from the country’s RIGI investment framework, offering fiscal stability and tax incentives. Galan’s Managing Director, Juan Pablo Vargas de la Vega, highlighted the team’s momentum and commitment as the project moves into its final construction and commissioning phase, signaling a promising transition to production.
Looking Ahead
As Galan Lithium approaches a critical milestone with the imminent commissioning of its nano-filtration plant and ongoing site works, the company is poised to join the ranks of lithium producers in 2026. The successful execution of Phase 1 will be a key indicator of its operational capabilities and market potential, while the exploration of capacity expansion hints at a broader growth trajectory.
Bottom Line?
Galan’s Hombre Muerto West project is on the cusp of production, with infrastructure en route and expansion plans brewing.
Questions in the middle?
- What is the detailed timeline for commissioning and ramp-up of the nano-filtration plant?
- How will potential expansion to 5,400 tpa LCE affect project economics and financing?
- What are the risks or contingencies if transit or installation of the nano-filtration plant face delays?