Read Story

Centaurus Secures Jaguar’s 20MW Power Link

9:53am on Friday 2nd of October, 2026 AEST
Key Points
  • 20MW of initial grid capacity secured
  • 230kV connection to run through a 36km transmission line
  • Environmental, mining and transmission easement approvals already in place
  • Aneel authorisation and a connection contract still required