Delorean clears funding hurdle for $62.1m Horsley Park bioenergy build
Delorean has reached Financial Close on its $62.1 million NSW1 Horsley Park bioenergy facility, activating $30.5 million of government grants and a 25-year Brickworks gas supply agreement. Procurement can now begin, with construction targeted for early 2027, although Tanarra’s debt documentation and the project’s funding mix still warrant attention.
- Financial Close reached on the 100%-owned NSW1 Horsley Park facility
- $30.5 million of NSW and federal government grants now active
- Executed $20 million Westpac trade finance facility supports equipment purchases
- Brickworks agreements provide a 25-year lease and renewable gas offtake
- $1.4 million placement priced at 6.7 cents a share, a 15% discount
Add us as a preferred source on Google
$62.1 Million Horsley Park Project Reaches Financial Close
Delorean Corporation Ltd (ASX:DEL) has cleared the funding hurdle that stood between its NSW1 Horsley Park bioenergy facility and construction. The company says Financial Close has been reached on the $62.1 million project, allowing procurement to start immediately and construction to move towards an early 2027 commencement.

The milestone activates two major government grants worth $30.5 million: $20 million from the NSW Government’s Net Zero Manufacturing Initiative and $10.5 million from ARENA’s National Industrial Transformation Program. It also brings into force the project’s long-term agreements with Brickworks subsidiaries, including a 25-year lease and a renewable gas supply agreement under which Brickworks will take the project’s output, subject to agreed maximum quantities.
Westpac Facility Converts Financing Mandate Into Project Debt
Horsley Park Bioenergy has executed a $20 million Westpac trade finance facility to fund equipment costs. The facility carries a line fee equal to 1% of the limit and interest at BBSY plus 2.5%, with Westpac taking senior security over the NSW1 project company. Delorean intends to refinance the trade facility into longer-term project debt once the plant is commissioned. The executed agreement replaces the earlier Westpac financing mandate, which had been non-binding.
The funding table also includes up to $10 million under a new Tanarra Facility D, alongside $1.6 million already spent on project capital costs, research and development tax refunds and future Delorean cash. Tanarra’s term sheet is described as binding, but full legal documentation remains outstanding. Its proposed economics include cash interest of BBSY plus 8%, 5% capitalising interest, a 3.25% commitment fee on undrawn tranches and staged equity options over the NSW1 project company if the facility is drawn.
Discounted Placement Adds Equity Ahead of Construction
Delorean has received firm commitments for a private placement of 20,895,523 shares at 6.7 cents each, raising $1.4 million before costs. The issue price represents a 15% discount to the 4 November closing price and a 22% discount to the 15-day VWAP. The new shares are expected to be allotted and begin trading on 17 November, with proceeds earmarked for NSW1, working capital and offer costs.
There is a small but notable discrepancy in the announcement: the placement is described as raising $1.4 million, while the project funding table allocates $1.3 million to the equity component. The remaining $8.7 million of the stated project funding is grouped together from Tanarra Facility D, R&D tax refunds and future cash on hand, making the timing and availability of those sources important to the build schedule.
Brickworks Offtake Anchors Renewable Gas Facility
NSW1 is designed to process 120,000 tonnes of source-separated organic waste each year, with approval for up to 150,000 tonnes, and produce approximately 253,000 gigajoules of mains-grade biomethane. The gas will be piped behind the meter to Brickworks’ Horsley Park manufacturing operations. Delorean says the project is expected to reduce the plant’s natural gas use by around 50% and Scope 1 emissions by approximately 38%.
The next test is execution rather than approval. Delorean Engineering is due to begin procurement and mobilise to site, while the company must complete Tanarra’s legal documentation and manage the staged drawdown of project funding. The facility’s economics will ultimately depend on construction progress, commissioning and the planned transition from Westpac trade finance to longer-term project debt.
Bottom Line?
Financial Close removes the main near-term funding obstacle, but Tanarra documentation, staged financing drawdowns and delivery of the early 2027 construction timetable remain the key execution tests.
Questions in the middle?
- When will full legal documentation for Tanarra Facility D be executed, and how much of the facility will be drawn?
- Can procurement and construction begin on schedule without requiring additional equity beyond the announced placement?
- How quickly can NSW1 reach commissioning and support the planned refinancing of Westpac’s trade facility?
Sources
1-
Financial Close Reached On NSW1 Horsley Park Bioenergy (opens in a new tab)Verified company source. Delorean Corporation Limited · 9 Nov 2026 · investorhub.deloreancorporation.com.au