29Metals clears Capricorn Copper hurdle as Golden Grove output accelerates

29Metals has secured preliminary Queensland approval for the tailings facility and water infrastructure needed to support a potential Capricorn Copper restart. Golden Grove also delivered its strongest monthly mining performance in more than three years, although federal approval, funding and a final investment decision remain outstanding.

  • Preliminary approval granted for Capricorn Copper’s TSF 3 and water treatment plant
  • 20-business-day objection period creates a further regulatory checkpoint
  • Federal EPBC process, funding and FID still required before restart
  • Golden Grove mined 156kt in October, its highest monthly volume in more than three years
  • Mill reached a 1.6Mtpa annualised run-rate during October
An image related to 29Metals Limited A photo of the logo for 29Metals Add us as a preferred source on Google
Image © middle. Logo © respective owner.

Capricorn Copper receives preliminary TSF 3 approval

29Metals Limited (ASX:29M) has cleared a major regulatory hurdle at its suspended Capricorn Copper operation, receiving preliminary approval for a new Tailings Storage Facility 3 and associated infrastructure. The approval is intended to support a restart, but it is not the final green light: eligible stakeholders have 20 business days to object, with the matter potentially referred to the Land Court.

Capricorn Copper mine site and approved TSF 3 design
Caption and image © 29Metals Limited. From “TSF Approval and Strong Operational Performance”, 17 Nov 2026.

TSF 3 is described by 29Metals as a critical enabler because it would provide a long-term tailings storage solution at Capricorn Copper. The planned project also includes a Water Treatment Plant designed to improve water management and mitigate the impact of future weather events. Detailed designs are being finalised, with construction tenders expected in 2027. The regulatory application had been a central condition of the restart case, as outlined in the earlier TSF 3 approval push.

Water inventory falls 2.3 gigalitres since suspension

The company says surface water inventory has fallen by 2.3 gigalitres, equivalent to about 900 Olympic-sized swimming pools, since operations were suspended in March 2024. Levels at the end of October were below both the Maximum Operating Level and the Design Storage Allowance compliance level specified in the Environmental Authority.

That improvement supports the company’s case that site water management has progressed, but the restart still depends on several unresolved steps. 29Metals remains on track to respond before year-end to a request for information from the federal Department of Climate Change, Energy, the Environment and Water as part of the EPBC referral process. The company describes this as the final approval required to enable a restart, while also noting that the restart Definitive Feasibility Study remains scheduled for completion by the end of 2026.

Funding proposals remain between approval and FID

29Metals is evaluating streaming, royalty and joint-venture proposals to fund the restart and reach a Final Investment Decision. No funding terms, restart date or project cost were disclosed in the announcement, leaving the economics of the next phase to be tested through the DFS and financing process.

The company has said Capricorn Copper could more than double its annual copper production if restarted. That remains a forward-looking ambition rather than current production: the operation has been suspended since March 2024, and construction of the newly approved infrastructure has not yet begun.

Golden Grove reaches 156kt monthly mining mark

While Capricorn Copper moves through approvals, Golden Grove supplied more immediate evidence of operating improvement. Ore mined reached 156kt in October, the highest monthly volume in more than three years, after 148kt in September. The increase came from additional ore sources across Gossan Hill and the recommencement of mining at Xantho Extended, a recovery effort that had been identified as important after the September quarter production setback.

An expanded seismic monitoring system recorded a modest response to the first Xantho Extended blast in 12 months, in line with expectations, according to the company. The second stope began firing on 15 November, while new access and bypass development continues. The mill also benefited from increased run-time after its 11-day September maintenance shutdown and high run-of-mine stock availability, producing an annualised throughput rate of 1.6 million tonnes in October.

First production from Oizon and first development ore from Gossan Valley remain scheduled before the end of 2026. Those milestones, alongside further Xantho Extended performance, will offer the next test of whether October’s stronger mining result can become a sustained improvement rather than a single-month peak.

Get ASX:29M news the moment it breaks

Instant push notifications No waitlist Free
Download on the App Store iPhone & iPad
Get it on Google Play Android
Email alerts

Bottom Line?

The approval moves Capricorn Copper closer to a restart, but the decisive tests are still ahead: federal clearance, financing, construction and FID.

Questions in the middle?

  • Will stakeholders challenge the preliminary approval during the 20-business-day objection period?
  • What funding structure and capital requirement will emerge from the restart DFS?
  • Can Golden Grove sustain October’s higher mining and milling rates as Xantho Extended, Oizon and Gossan Valley progress?