Metallium takes paid MXene program into upgraded Texas reactor
Metallium has commissioned an upgraded Flash Joule Heating reactor in Texas for its first commercial technology-services program beyond metals recovery. The early-stage MXene campaign is funded by Environmental Clean Technologies and could generate up to US$1.4 million over 12 months while Metallium retains its reactor and process intellectual property.
- Upgraded reactor passes cold and hot commissioning at Gator Point
- Initial campaign will process approximately 400 grams of MXene precursor
- US$500,000 received upfront, with US$225,000 quarterly fees
- On-site X-ray diffraction analysis to support batch optimisation
- Second reactor upgrade underway alongside the first campaign
Add us as a preferred source on Google
Paid MXene program moves into reactor testing
Metallium Limited (ASX:MTM) has moved its first paid technology-services program beyond metals recovery into live reactor testing, commissioning an upgraded Flash Joule Heating system at its Gator Point campus in Texas. The first campaign for Environmental Clean Technologies Limited (ASX:ECT) is scheduled to begin this week, using approximately 400 grams of titanium aluminium carbide precursor to produce titanium carbide MXene.

The commissioning milestone is commercially important because the work is funded by ECT rather than Metallium’s own development budget. The company has received a US$500,000 upfront payment and is due to receive US$225,000 per quarter in engineering support and facility fees, taking total cash consideration to as much as US$1.4 million over the initial 12-month term. ECT has also issued Metallium 20 million options exercisable at A$0.18 and expiring 12 months after issue.
On-site analysis becomes the next optimisation tool
The campaign will test more than whether the reactor can produce MXene. Metallium says the focus is now conversion, consistency between batches and assessing the resulting material against application requirements. A newly procured X-ray diffractometer allows samples to be analysed at Gator Point, so the results from one run can inform the conditions used in the next.

That capability builds on the first MXene program payment reported earlier, when Metallium said its on-site laboratory had been expanded with X-ray diffraction and thermogravimetric analysis equipment. ECT reported MXene formation in its first two runs on Metallium’s FJH platform on 9 October, but the current campaign is intended to improve repeatability rather than establish commercial production.
Reactor and process IP stays with Metallium
The arrangement gives ECT ownership of the MXene product while Metallium retains its existing and future reactor and process intellectual property. The company describes this as the technology-services model outlined at its 2026 annual meeting: a partner funds a new application, while Metallium supplies reactor access, engineering support and technical expertise. Any longer-term licence or royalty arrangement remains subject to further agreement.
The chemistry also has a direct connection to Metallium’s critical-metals work. FJH chlorination selectively removes aluminium from the MAX-phase precursor, leaving thin titanium carbide sheets. The same heating and chlorination capabilities are being developed for gallium, germanium and other metals at Gator Point, while the MXene program runs alongside the company’s PCB processing program.
Second reactor and December update set the next tests
Cold commissioning verified the upgraded system’s equipment, utilities, instrumentation, controls, leak integrity, safety interlocks and shutdown functions. Hot commissioning then confirmed heating performance, temperature control at the target setpoint and operation of the chlorination off-gas scrubbing system.
A second reactor upgrade is now underway, incorporating improvements from the first system. Metallium expects to report on the initial campaign and the second reactor in its December quarter report, subject to testing and validation. Until those results arrive, the program’s commercial promise rests on an early development campaign rather than validated conversion, product qualification or scaled production.
Bottom Line?
The reactor is commissioned and the revenue framework is in place; the decisive evidence will be whether repeated batches meet ECT’s application requirements and lead to a longer-term commercial arrangement.
Questions in the middle?
- Will the 400-gram campaign deliver consistent conversion and product characteristics across batches?
- Can ECT qualify the MXene for its intended defence and electronics applications?
- Will the program progress from quarterly service fees to a longer-term licence or royalty agreement?