Jade Opens New Red Lake Test With Mongolia’s First Multilateral CBM Well
Jade Gas has completed Mongolia’s first multilateral coal bed methane well at Red Lake ahead of schedule, with 2,642 metres drilled within the target coal seam. The technical milestone now faces its more consequential test: coordinated dewatering and production testing across three wells.
- First multilateral CBM well completed at Red Lake
- 2,642 metres of in-seam drilling across four lateral branches
- Pump installed and workovers underway on two existing wells
- Coordinated dewatering expected before the end of November
- Results to shape Jade’s targeted 2027 development drilling programme
Add us as a preferred source on Google
Red Lake Well Completed Ahead of Schedule
Jade Gas Holdings Limited (ASX:JGH) has completed Mongolia’s first multilateral coal bed methane well ahead of its end-November target, delivering an operational milestone at the Red Lake area of its flagship Tavantolgoi XXXIII project.


The RL-001-3b-ML-03 well combines a main wellbore with four lateral branches targeting Seam IIIb. Drilling contractor Yan’an Drilling Wellking Energy Technical Service completed 2,841.6 metres of horizontal drilling, including 2,642 metres within the target coal seam. Jade said the in-seam portion represented about 93% of the combined horizontal sections.

The result advances the design being tested in Jade’s first multilateral well drilling, which was previously described as a five-branch configuration intended to inform future production planning. Real-time geosteering guided the well through the coal, with a slotted liner installed in the main wellbore and the four lateral branches completed open-hole.
Three-Well Dewatering Test Moves Next
Jade has installed a progressive cavity pump and wellhead motor on the new well, while trenching for water and gas pipelines has been completed. Workovers and maintenance are now underway on the two existing single-lateral wells, HZ01 and HZ02, ahead of planned simultaneous dewatering of all three wells before the end of November.
That testing phase matters more than the drilling milestone alone. Jade says monitoring the wells together will provide data on reservoir pressure responses, water production and gas flow, allowing operational adjustments and an assessment of the new well’s gas-production capability. The company has not disclosed a production rate or commercial flow result from the completed well.
Technical Results to Shape 2027 Drilling
The multilateral layout is intended to increase contact with gas-bearing coal from a single wellbore, with potential benefits including a larger drainage area, improved recovery and higher flow rates. Those benefits remain unconfirmed until dewatering and production testing are complete.
Jade plans to use the drilling, pressure and production data to refine future well configurations, lateral layouts, completion practices, equipment requirements and drilling schedules for a development programme targeted for 2027. That programme sits alongside the company’s proposed Red Lake funding, but this announcement provides no update on whether that proposed financing has become binding.
Bottom Line?
The well has answered the construction question; the next few weeks must show whether its extra reservoir contact translates into sustained gas flow.
Questions in the middle?
- When will coordinated dewatering begin, and what pressure and water responses will the three-well system produce?
- What gas-flow rate and production profile will the new multilateral well achieve after dewatering?
- Will the test results support the well designs and scale envisaged for Jade’s 2027 development programme?
Sources
1-
JGH Completes Multilateral CBM Well Ahead of Schedule (opens in a new tab)Verified source. Jade Gas Holdings Limited · 19 Nov 2026