St Barbara lines up cash and production as Nova Scotia strategy accelerates

St Barbara is moving from asset sales to project delivery, with a potential A$453 million Simberi exit, Touquoy’s first gold targeted for January and A$475 million already in the bank. The main uncertainty is whether regulatory delays will slow its larger 15-Mile development in Nova Scotia.

  • A$475 million cash, no debt and no hedging at FY26 year-end
  • A$453 million Simberi sale targeted for the March quarter of 2027
  • Touquoy expected to produce 38,000 ounces over 13 months
  • 15-Mile hub forecasts 106,000 ounces a year over a 13-year mine life
  • Federal impact assessment adds uncertainty to the 15-Mile timetable
An image related to St Barbara Limited A photo of the logo for St Barbara Add us as a preferred source on Google
Image © middle. Logo © respective owner.

Simberi sale could reshape St Barbara’s balance sheet

St Barbara Limited (ASX:SBM) is entering FY27 with a cash-rich balance sheet and a portfolio increasingly centred on Nova Scotia, after setting out the next steps for its Simberi exit and Touquoy restart at its annual general meeting.

The company ended FY26 with A$475 million in cash, no debt and no hedging. It is also targeting A$453 million in cash from the sale of its remaining New Simberi Gold interest to Lingbao Gold, a transaction expected to complete in the March quarter of 2027 subject to regulatory approvals in China and Papua New Guinea. St Barbara will retain a 2.75% net smelter return royalty over future gold and silver production from New Simberi Gold, plus a 1.5% royalty over future mineral production from the Tabar Island Group exploration licences.

The proposed exit was detailed in A$453m Simberi exit, which reported that the deal could support further shareholder distributions while funding Nova Scotia development. The chair’s address says the board will consider further dividends while balancing capital requirements for exploration and project development.

Touquoy moves from restart to production

The immediate operating test is Touquoy. Processing of stockpiled ore has recommenced in Nova Scotia, with first gold pour expected in January 2027. St Barbara expects the restart to produce 38,000 ounces over 13 months and generate C$118 million in operating cash flow, based on an assumed gold price of US$4,000 an ounce.

The figures are forward-looking rather than reported outcomes, but the project has already moved into physical operations. Touquoy is expected to add C$158 million to Nova Scotia’s gross domestic product and support 118 permanent jobs, including former employees returning to the operation. Earlier coverage recorded that processing restarted on schedule and that first gold doré was targeted for January 2027.

15-Mile project faces an additional federal assessment

St Barbara’s larger growth option is the 15-Mile Processing Hub, where a September update outlined a 13-year mine life, average annual production of 106,000 ounces and an all-in sustaining cost of US$1,098 an ounce. Permitting began in June, but the Impact Assessment Agency of Canada has since required a federal impact assessment that St Barbara describes as duplicative.

The company says the extra process was required despite the federal government’s stated goal of “One Project, One Review”. Chief executive Andrew Strelein is meeting Canadian and Nova Scotian regulators and governments to understand the scope of the assessment and its potential effect on the targeted timetable. The additional permitting work had already been identified as a risk to the project’s construction schedule.

Headline profit reflects a major transaction

St Barbara reported a statutory FY26 profit after tax of A$490 million, including a A$500 million gain from deconsolidating New Simberi Gold. That accounting gain means the headline result should not be read as a measure of recurring operating earnings. The company invested A$78 million in growth capital, exploration, evaluation and feasibility work during the year, while declaring a fully franked dividend of A$0.05 a share paid on 16 October.

Its FY27 agenda is therefore unusually clear: complete the Simberi sale, convert Touquoy’s restart into gold production and keep the 15-Mile approval process moving. The key tension is whether the balance sheet can advance the next Nova Scotia project at the pace implied by the strategy while the additional federal assessment remains unresolved.

Get ASX:SBM news the moment it breaks

Instant push notifications No waitlist Free
Download on the App Store iPhone & iPad
Get it on Google Play Android
Email alerts

Bottom Line?

The next value test is execution: Touquoy must deliver its January first pour, while Simberi approvals and the 15-Mile assessment will determine how quickly St Barbara can deploy its strengthened balance sheet.

Questions in the middle?

  • Will the Simberi sale receive all required approvals in time for the targeted March quarter 2027 completion?
  • Can Touquoy meet its January first-gold target and approach the forecast C$118 million operating cash flow?
  • How much will the additional federal assessment change the timetable or funding requirements for the 15-Mile Processing Hub?