Forrestania lines up Edna May operations ahead of first gold target
Forrestania Resources has secured cyanide supply, appointed an ore-handling contractor and opened a Kalgoorlie operating hub as it prepares Edna May for production. The company says dry commissioning is underway and continues to target a first gold pour in December 2026.
- Long-term sodium cyanide supply secured for Edna May
- Campbell Gold Haulage awarded ore loading and crusher feed work
- Approximately 60,000 tonnes of ore available at Edna May
- Lake Johnston ore inventories exceed 180,000 tonnes
- Kalgoorlie operations hub led by Darren Gaby established
Add us as a preferred source on Google
Edna May moves from commissioning towards production
Forrestania Resources Limited (ASX:FRS) has begun locking in the operating pieces needed to turn Edna May from a commissioned plant into a producing gold mine, securing critical reagent supply and ore-handling capacity ahead of a targeted first gold pour in December 2026.

The company has signed a long-term sodium cyanide supply agreement with Australian Gold Reagents, securing a reagent required for gold recovery. It has also awarded Campbell Gold Haulage the contract for ore loading and crusher feed, with equipment and personnel mobilisation underway. Forrestania said the arrangement supports ore handling and plant feed requirements at both Edna May and Lake Johnston, while Campbell’s existing road train contract creates an operational link at the ROM pads.
Ore inventories provide the immediate feedstock
Executive Chairman David Geraghty said approximately 60,000 tonnes of ore was available on the Edna May ROM, with first ore processing “fast approaching”. Lake Johnston held more than 180,000 tonnes, with its ROM stockpile described as near full capacity.

The update adds practical detail to the commissioning timetable, which has been a recurring feature of Forrestania’s recent production narrative. The company previously reported that Edna May dry commissioning was underway while building a third-party mill-feed pipeline, but today’s announcement focuses on the less glamorous and more immediate question of whether the plant has the materials, logistics and people required to operate.
Kalgoorlie hub adds operational leadership

Forrestania has established a dedicated office in Kalgoorlie to support its Goldfields workforce. The facility will be shared with MEGA Resources and led by newly appointed General Manager Mining Darren Gaby, who has more than 30 years of Western Australian Goldfields experience, including leading Beacon Minerals’ Jaurdi Gold Project from construction through to production.
The announcement does not disclose the value of the cyanide or haulage contracts, nor does it provide production rates, operating costs or a binding delivery date for first gold. That leaves the December target dependent on the remaining commissioning and operating steps, including the transition from dry to wet commissioning. The next hard evidence will be the start of first ore processing and whether mobilisation, reagent deliveries and stockpile handling translate into a sustained production run.
Bottom Line?
Forrestania has reduced several obvious readiness gaps at Edna May, but the December gold-pour target still has to survive wet commissioning and the first full operating sequence.
Questions in the middle?
- When will Edna May begin processing ore and move from dry to wet commissioning?
- What production rates, recovery assumptions and operating costs will Forrestania disclose once the plant is running?
- Can Lake Johnston’s large stockpile and Campbell’s logistics platform support consistent feed beyond the initial Edna May restart?
Sources
1-
Forrestania Advances Edna May Production Readiness (opens in a new tab)Verified company source. Forrestania Resources Limited · 20 Nov 2026 · investors.forrestaniaresources.com.au