Forrestania Resources has delivered first ore into the primary crusher at its Edna May Gold Mine, with wet commissioning now underway. The company still targets first gold production in December 2026, but plant performance and timing remain unproven until commissioning is completed.
- First ore delivered into Edna May’s primary crusher
- Wet commissioning underway across key processing circuits
- First gold production remains targeted for December 2026
- Combined ROM stockpiles exceed 250,000 tonnes
- SAG mill liners are on site for installation
First Ore Reaches Edna May Crusher
Forrestania Resources Limited (ASX:FRS) has moved its Edna May Gold Mine into wet commissioning after feeding first ore into the operation’s primary crusher. The milestone puts the company closer to its targeted first gold production in December 2026, although the date remains a target rather than a confirmed production start.
The delivery came roughly 11 weeks after Forrestania took operational control of Edna May on 4 September. It follows the company’s Edna May commissioning push, which had included dry commissioning and preparations for a December first gold pour.
Wet Commissioning Begins Across Processing Plant
Ore is now passing through the crusher as Forrestania works through a staged commissioning program. The company said testing and optimisation will continue across key process plant circuits before first gold production, meaning the next operational evidence will matter more than the headline milestone itself: throughput, recoveries, plant stability and the timing of the first pour have not yet been disclosed.
SAG mill liners are on site for installation, while combined run-of-mine stockpiles at Edna May and Lake Johnston exceed 250,000 tonnes. That inventory gives Forrestania material on hand for commissioning and future processing, but the announcement does not provide production-rate, cost, recovery or revenue guidance.
Two Processing Hubs Support Larger Resource Base
Forrestania also used the operational update to point to the scale of its transformation over the past year. It said its Mineral Resource inventory has grown from approximately 300,000 ounces to more than 3 million ounces, alongside control of Zenith Minerals and the establishment of processing hubs at Edna May and Lake Johnston.
That broader strategy gives the company a larger pool of potential ore sources, but the immediate test is narrower and more practical: whether Edna May can move from wet commissioning to reliable gold production on the December timetable. Until that transition is demonstrated, the resource growth remains a longer-term platform rather than evidence of near-term output.
Bottom Line?
The crusher milestone reduces one execution hurdle, but the investment case now turns on commissioning performance and whether first gold arrives in December 2026.
Questions in the middle?
- Can Edna May complete wet commissioning and deliver first gold within the December 2026 target?
- What throughput, recovery and production rates will emerge once the plant enters steady operation?
- How quickly can the more than 250,000 tonnes of stockpiled ore translate into sustained processing activity at both hubs?