GR Engineering secures most of a major FY27 revenue leap
GR Engineering Services Limited (ASX:GNG) reported record FY26 EBITDA of $63.1 million and raised its fully franked annual dividend to 25.0 cents per share. Its FY27 revenue forecast of $825 million to $850 million is more than 90% secured at the high end, although the expansion has required a $110 million equity raising to support working capital.
- Record FY26 EBITDA of $63.1 million
- FY27 revenue guidance of $825 million to $850 million
- More than 90% of high-end FY27 revenue contracted
- $110 million placement and share purchase plan completed
- FY26 fully franked dividends increased to 25.0 cents per share
Add us as a preferred source on Google
Contracted work underpins a major FY27 revenue step-up
GR Engineering Services Limited (ASX:GNG) is heading into FY27 with a much larger revenue base already in sight. The engineering and services group expects revenue of $825 million to $850 million, equivalent to a 67% to 72% increase on FY26 revenue of approximately $493 million, with more than 90% of the high-end forecast secured through contracted projects.
The forecast is not a guaranteed outcome. GR Engineering says it is a non-IFRS measure based on the same assumptions and methodology used in prior forecasts, including similar contributions from studies, minor works and other new work and no change in market conditions. That leaves a portion of the target dependent on work yet to be awarded or converted, even as the company continues building its contracted pipeline for FY27 and FY28.
Record EBITDA and higher shareholder distributions
FY26 delivered revenue of $493.2 million in the executive summary, although another section of the presentation rounds the figure to $493.0 million. EBITDA reached a record $63.1 million, up from $57.2 million, while the board increased the final dividend to 13.0 cents per share. Total FY26 dividends rose to 25.0 cents per share, fully franked, from 22.0 cents a year earlier.
The result builds on the company’s previously outlined FY27 contract pipeline, which included more than $1 billion in new awards since 1 April 2026. GR Engineering says roughly 60% of forecast FY27 revenue from the current contracted pipeline is expected to come from commodities other than gold, offering some diversification across the resources cycle without removing exposure to project delivery conditions.
$110 million raise strengthens delivery capacity
The company has also finished building a larger financial buffer for the workload ahead. An institutional placement raised $100 million and a share purchase plan added $10 million, both at $6.10 per share. GR Engineering says the proceeds will fund working capital for recent and new contracts, provide flexibility for possible acquisitions and support investment in internal IT infrastructure and resourcing.
At 30 June 2026, net cash stood at $87.9 million, compared with $70.9 million a year earlier. On a pro forma basis after the raising, cash was approximately $198 million with nil debt. Operating cash inflows were $62.6 million during FY26, while capital expenditure remained modest at $3.2 million. The capital raise therefore sits less as a repair of the balance sheet than as funding capacity for a business expecting significantly more activity, though the cash requirement of executing larger projects remains an issue to track.
Mining, energy and automation projects fill the pipeline
GRES, the group’s engineering, design and construction arm, was working across projects including the $275 million Yitirrti Copper-Silver-Zinc project, the $233 million Davyhurst Expansion Project, BHP’s $230 million Yandi upgrade and the $110 million Laverton Processing Plant. It was also engaged on 28 studies across multiple commodities and geographies at 31 October 2026.
GR Production Services added longer-duration energy revenue through operations and maintenance work, including a five-year, $57 million contract for the Sturt Plateau Compression Facility in the Northern Territory, with an option for a further three years. Mipac and Paradigm also reported a larger contracted pipeline for process-control, automation and digital work with repeat clients including BHP, Rio Tinto, First Quantum Minerals and Anglo American.
Execution becomes the central test
The presentation’s central tension is straightforward: the revenue visibility is unusually strong, but converting that visibility into earnings and cash will depend on delivering a much larger volume of work. GR Engineering completed the King of the Hills Upgrade, Eloise Copper Expansion and Dalgaranga Paste Plant projects after the end of FY26, while other major projects remain in execution.
The next evidence will come from project progress, margins and working-capital movements rather than from the headline order book alone. The unsecured portion of FY27 guidance, the economics of any acquisitions and the company’s ability to scale internal systems without diluting returns will determine how much of the promised step-change reaches shareholders.
Bottom Line?
GR Engineering enters FY27 with substantial contracted revenue and a stronger balance sheet, but delivery discipline and cash conversion now matter as much as new contract wins.
Questions in the middle?
- How much margin will the larger FY27 project mix generate once execution is underway?
- Can the company convert its studies and early works pipeline into additional contracted revenue without stretching working capital?
- Will the strengthened balance sheet be used for acquisitions, internal capability or further project funding first?
Sources
1-
FY26 Annual General Meeting Presentation (opens in a new tab)Official market announcement. Gr Engineering Services Limited · 25 Nov 2026 · gres.com.au