Delorean Corporation and Opal have completed the concept stage for a proposed anaerobic digestion facility at Opal’s Maryvale Mill in Victoria. The project could replace natural gas used by the mill’s rotary lime kiln, but still requires further engineering, commercial work and a final investment decision.
Victor Sage
Victor Sage
23 Sept 2026
Delorean Corporation’s SA1 Salisbury bioenergy project has secured accreditation under GreenPower’s Renewable Gas Certification, enabling it to issue Renewable Gas Guarantee of Origin certificates and strengthen its role in Australia’s renewable gas market.
Maxwell Dee
Maxwell Dee
10 June 2026
Delorean’s flagship SA1 Salisbury bioenergy plant is 75% complete, poised to start injecting renewable biomethane into Adelaide’s gas network by November 2026, marking a first in Australia for commercial and industrial organic waste processing.
Maxwell Dee
Maxwell Dee
25 May 2026
Delorean Corporation reported solid progress in Q3 FY2026, including a positive Final Investment Decision for its NSW1 Horsley Park bioenergy facility backed by $30.5 million in grants, alongside ongoing construction at its flagship SA1 Salisbury project.
Victor Sage
Victor Sage
30 Apr 2026
Delorean Corporation has secured a $1.1 million milestone payment from ARENA, marking significant progress on its SA1 Salisbury bioenergy facility. Construction advances and long-term contracts position the project for renewable gas production in South Australia.
Victor Sage
Victor Sage
6 Mar 2026
Delorean Corporation reports a significant half-year loss as it pivots from contractor to bioenergy infrastructure owner, advancing key projects but facing financial covenant breaches.
Maxwell Dee
Maxwell Dee
26 Feb 2026
Delorean Corporation has completed the $53 million Yarra Valley Water bioenergy facility and progressed key projects in South Australia and Victoria, supported by strong government grants and renewable gas policies.
Victor Sage
Victor Sage
30 Jan 2026
Delorean Corporation marks a pivotal shift to build-own-operate bioenergy projects with the completion of its $53 million Yarra Valley Water facility and strong progress on its SA1 Salisbury project, backed by $51.5 million in financing and robust market demand.
Maxwell Dee
Maxwell Dee
28 Nov 2025
Delorean Corporation has teamed up with Paper Australia (Opal) to explore a renewable energy project at the Maryvale Paper Mill, aiming to convert organic waste into green gas and electricity through anaerobic digestion.
Victor Sage
Victor Sage
26 Nov 2025
Delorean Corporation has transitioned to the operations and maintenance phase at its $53 million Yarra Valley Water bioenergy facility, marking a key milestone in its renewable energy expansion.
Victor Sage
Victor Sage
27 Oct 2025
Delorean Corporation has applied for Practical Completion of its Yarra Valley Water bioenergy facility, signaling readiness to transition into operations and maintenance. This milestone sets the stage for an $8 million contract phase and highlights the company’s growing footprint in renewable energy.
Victor Sage
Victor Sage
14 Oct 2025
Fluence Corporation Limited reported a robust 64.5% revenue increase in Q1 2025, driven by a strategic pivot to higher-margin Smart Product Solutions and recurring revenue streams, while maintaining its full-year guidance.