QPM Energy Limited has voluntarily suspended its ASX securities pending a significant announcement on a strategic investment and capital raising, expected by December 4, 2025.
Maxwell Dee
Maxwell Dee
3 Dec 2025
QPM Energy has made significant strides in advancing its 112MW Isaac Power Station, securing major financing and operational milestones that position it well for mid-2027 commissioning.
Maxwell Dee
Maxwell Dee
29 Oct 2025
QPM Energy has initiated funding under its $113.7 million Master Lease Agreement with Macquarie Bank and triggered equipment delivery from GE Vernova, marking a key milestone in its project development.
Maxwell Dee
Maxwell Dee
16 Oct 2025
QPM Energy has secured a $113.7 million lease agreement with Macquarie Bank to fund key gas turbines for its Isaac Power Station, reinforcing its mid-2027 commissioning goal. This milestone advances the project closer to final investment decision amid ongoing engineering and approvals.
Maxwell Dee
Maxwell Dee
10 Oct 2025
QPM Energy has reported its first-ever profit alongside a 12.6% revenue increase and significant growth in gas reserves and electricity generation capacity.
Maxwell Dee
Maxwell Dee
23 Sept 2025
QPM Energy Limited has completed commissioning of its Townsville Power Station and initiated a pivotal Dispatch Agreement with Ratch Australia Corporation, setting the stage for enhanced electricity market participation.
Maxwell Dee
Maxwell Dee
4 Aug 2025
QPM Energy has launched its Isaac Energy Hub and completed a major overhaul of the Townsville Power Station, setting the stage for a final investment decision on its Isaac Power Station by year-end.
Maxwell Dee
Maxwell Dee
30 July 2025
QPM Energy has successfully completed major commissioning runs at its Townsville Power Station, generating over 4,700 MWh and preparing to take operational control. Final steps are underway to leverage new gas agreements and electricity market opportunities.
Maxwell Dee
Maxwell Dee
29 July 2025
QPM Energy has secured Northern Australia Infrastructure Facility approval to enter due diligence for financing its 112MW Isaac Power Station, marking a key step toward final investment decision by late 2025.
Maxwell Dee
Maxwell Dee
28 July 2025
QPM Energy has successfully raised $7 million through an oversubscribed Share Purchase Plan, significantly exceeding its initial $2 million target to accelerate key gas power projects in Queensland.
Maxwell Dee
Maxwell Dee
23 July 2025
QPM Energy Limited has launched a $2 million Share Purchase Plan at $0.031 per share, matching a recent $10 million placement, to support the development of its Isaac Energy Hub. Eligible shareholders in Australia and New Zealand can participate until mid-July.
Maxwell Dee
Maxwell Dee
4 July 2025
QPM Energy Limited has launched the Isaac Energy Hub, beginning with a 112MW gas-fired power station aimed at bolstering Queensland’s transition to a low-carbon electricity grid by mid-2027.