Lotus Resources Advances Acid Supply Chain, Delays Full Uranium Output to Q2 2026

Lotus Resources has made significant progress resolving sulphuric acid supply issues critical to ramping up production at its Kayelekera Uranium Mine, though full steady-state output is now expected in the second quarter of 2026.
Maxwell Dee
29 Jan 2026

Lotus Resources Delivers First High-Grade Ore, Eyes Steady Production in Q1 2026

Lotus Resources has achieved a key milestone at its Kayelekera Uranium Mine with the first high-grade ore delivered to the ROM pad, setting the stage for steady-state production targeted in early 2026. The company has also secured multiple sulphuric acid suppliers and is on track to commission its acid plant to ease supply constraints and reduce costs.
Maxwell Dee
23 Dec 2025

Lotus Resources Proposes 11.5-for-1 Share Consolidation to Boost Investor Appeal

Lotus Resources plans a significant share consolidation to better align its capital structure with its ASX300 status, aiming to attract a broader investor base. The move, subject to shareholder approval, coincides with a proposed update to the company’s constitution.
Maxwell Dee
10 Dec 2025

Lotus Resources Nears Steady State at Kayelekera Amid Acid Supply Challenges

Lotus Resources reports promising progress at its Kayelekera uranium mine, targeting steady state production by Q1 2026 despite recent sulphuric acid supply constraints. The company is addressing supply issues with new sourcing and an on-schedule acid plant rebuild.
Maxwell Dee
4 Dec 2025

Lotus Resources Hits First Yellowcake at Kayelekera, Eyes Full Production in 2026

Lotus Resources has marked a major milestone with first yellowcake production at its Kayelekera uranium mine in Malawi, progressing steadily towards full production in early 2026 while advancing its Letlhakane project in Botswana.
Maxwell Dee
30 Oct 2025

Lotus Resources Secures A$65M to Fuel Uranium Growth in Africa

Lotus Resources has completed a A$65 million placement to bolster its uranium projects in Malawi and Botswana, positioning itself for steady production and future expansion.
Maxwell Dee
4 Sept 2025

Lotus Resources Drums First Yellowcake at Kayelekera, Eyes 200,000 lbs Monthly Output

Lotus Resources has achieved a pivotal milestone by producing its first yellowcake at the Kayelekera Uranium Mine, marking its emergence as a global uranium producer. The company targets ramping up production to 200,000 pounds per month by early 2026.
Maxwell Dee
1 Sept 2025

Lotus Resources Secures Final Approval to Restart Kayelekera Uranium Mine

Lotus Resources has received the final environmental and social approval to restart its Kayelekera Uranium Mine in Malawi, marking a key milestone in its African uranium operations. This endorsement from Malawi’s Environment Protection Authority paves the way for the company’s planned production ramp-up.
Maxwell Dee
5 Aug 2025

Lotus Resources Powers Ahead with Kayelekera Uranium Restart and Binding Offtake Deals

Lotus Resources is on track to restart uranium production at its Kayelekera project in Malawi by Q3 2025, backed by binding offtake contracts covering nearly 4 million pounds of uranium and a robust cash position.
Maxwell Dee
31 July 2025

Lotus Resources Begins High-Grade Uranium Processing at Kayelekera, First Production Imminent

Lotus Resources has initiated processing of high-grade uranium ore at its Kayelekera Project in Malawi, moving closer to first uranium production this quarter. Key infrastructure upgrades, including a new power grid connection, aim to reduce costs and environmental impact.
Maxwell Dee
31 July 2025

Lotus Resources Restarts Kayelekera Mill, Eyes Uranium Output This Quarter

Lotus Resources has completed key refurbishments at its Kayelekera Uranium Project in Malawi, restarting the SAG mill and progressing through hot commissioning towards first uranium oxide production this quarter.
Maxwell Dee
14 July 2025

Lotus Advances Kayelekera Restart with Owner-Operator Mining Shift

Lotus Resources has begun cold commissioning at its Kayelekera uranium project, targeting a Q3 2025 production restart while adopting an owner-operator mining model to reduce costs and enhance control.
Maxwell Dee
17 June 2025